JUNE 2020

PROJECT COMPLETED
  • More than 70% Villaments Sold and Occupied
  • Villaments ready for interior work and furnishing.
  • Water, BESCOM connection, STP, Elevators, Back-up power, maintenance, all amenities etc operational.

DECEMBER 2018 REPORT

Highlights
 
  • Club House completed & operational.
  • Villaments now ready for interior work and furnishing.
  • Water, BESCOM connection, STP, Elevators Back-up power, maintenance, all amenities etc operational.

AUGUST 2018 REPORT

Highlights
 
  • VDF flooring completed for basement parking.
  • Ground level driveway completed.
  • Planter box & landscaping completed.
  • Elevator installation, staircase & ramp for wheel-chair access completed. 
  • Transformer installation completed.
  • External painting completed.
  • Electrical work for villaments in-progress.
  • Amenities work in-progress.
  • STP, Rain Water Harvesting & Pump room completed.
  • Plumbing work completed.
  • Elevators testing in-progress.

APRIL 2018 REPORT

Highlights
 
  • 2-BHK & 3 BHK villaments ready for interior work.
  • Interior plastering completed.
  • Front and side elevation completed.
  • Virtrifed flooring & bathroom tiles for all villaments completed.
  • Driveway flooring in-progress.
  • Amenities work in-progress
  • Planter box & landscaping along the driveway.
  • STP & rain water harvesting plant work in-progress.

OCTOBER 2017 REPORT

Highlights
 
  • 2-BHK & 3 BHK Model Units completed.
  • Front elevation work in-progress.
  • Interior plastering 80% completed.
  • Exterior plastering 90% completed.
  • Virtrifed flooring for 2-BHK and 3-BHK apartments on G & 1st & 2nd floor completed.
  • Drive way completed.

AUGUST 2017 REPORT

Highlights
 
  • 2-BHK & 3 BHK Model Units to be open soon !
  • Basement, G, 1st, 2nd & 3rd floor structure completed
  • Exterior plastering 90% completed
  • Interior walls completed
  • Internal plastering & Electrical works 60% completed
  • Virtrifed flooring for 2-BHK and 3-BHK apartments on G & 1st floor completed.
  • Drive way in progress

FEBRUARY 2017 REPORT

Highlights
 
  • 2-BHK & 3 BHK Model Units in-progress.
  • Basement, Ground Floor, 1st Floor & 2nd Floor slab/roof completed
  • 3rd Floor (E & F Block) slab completed
  • Retaining walls on 3 sides completed
  • Internal plastering & Electrical works for 2-BHK and 3-BHK model units completed

OCTOBER 2016 REPORT

Highlights
 
  • GF slab for C, D, E & F block completed
  • Basement slab for all blocks completed
  • Retaining wall on east, west and south side

JANUARY 2016 REPORT

Highlights
 
  • Footings for Block E & Block F
  • Footings for Club House
  • Retaining wall on south side completed

AUGUST 2015 REPORT

Highlights
 
  • Site inaugurated.
  • Site cleaning and levelling.
  • Site office constructed.